Water Supply - Dwr Cymru Welsh Water has made representations on planning application ref 2023/00051/HYB. A hydraulic modelling assessment (HMA) will be required. A 160mm diameter watermain, and a 3” diameter abandoned watermain cross the site.
Wastewater - Dwr Cymru Welsh Water has made representations on planning application ref 2023/00051/HYB. The public sewerage network can accept potential foul flows from this development site.
A 1050mm surface water sewer crosses the site.
Wastewater Treatment Works - Dwr Cymru Welsh Water has made representations on planning application ref 2023/00051/HYB. Cog Moors WwTW has capacity to accept foul flows from the proposed development.