1 Ymgynghoriad ar Cynllun Datblygu Lleol Newydd

ID sylw: 6929

Derbyniwyd: 11/03/2026

Respondent ID: 2669

Ymatebydd: Barratt Redrow Homes

Asiant : Boyer Planning

Crynodeb o'r Gynrychiolaeth:

Whilst we understand that the proposed developer, Edenstone Homes, has recently engaged with the Council through its pre-application service. According to the Council’s planning register, no formal planning application has been submitted to date. As such, there remains no
confirmed development proposal, agreed technical evidence base, or indicative determination timeframe associated with the allocation.

In the absence of a live application, there is a considerable degree of uncertainty surrounding the anticipated delivery programme. The housing trajectory assumes development commencing in 2027/28; however, this appears optimistic given that an application has yet to
be submitted, validated or determined. Even following any grant of planning permission, there would be a requirement to discharge pre-commencement conditions and satisfy any relevant planning obligations before development could lawfully begin. From experience these
processes can be time-consuming and may result in significant delays with regards to lead-in times prior to first completions.

Given this uncertainty, reliance on the site to deliver within the early phases of the plan period carries risk. It is therefore important that the emerging RLDP identifies a broader and more diverse portfolio of deliverable site allocations to support housing delivery, particularly in the
earlier years of the plan. Incorporating additional sites with stronger prospects of short-term delivery will provide flexibility, resilience, and greater confidence in maintaining a robust housing land supply should delays arise on this allocation.