Cynllun Adneuo - Atodiad

Yn dangos sylwadau a ffurflenni 1 i 6 o 6

Sylw

2 Dogfennau Ategol

ID sylw: 5128

Derbyniwyd: 04/03/2026

Respondent ID: 2386

Ymatebydd: Welsh Government (Planning Division)

Crynodeb o'r Gynrychiolaeth:

Delivery and Implementation
PPW and the DPM (Chapter 5) contain guidance on the requirements in respect of the delivery and implementation of plans. The Deposit Plan should set out site-specific details for Key Sites that includes general phasing timescales, key infrastructure requirements, placemaking principles (including concept / schematic masterplan frameworks), constraints, and developer requirements, where appropriate. We note the Deposit Plan has included emerging master planning/infrastructure work on key sites.

The phasing, timing, funding, and delivery of Key Sites will be critical to ensure the plan delivers the scale of growth required over the plan period. This includes the relationship between the two Key Sites in St Athan (KS4 and KS5) totalling up to 1,150 units and the delivery of a new rail station in St Athan to meet the objectives of the strategy and encourage a modal shift to more sustainable forms of public transport.

The development sites may also impact on the trunk road network, in particular the M4 J34 and there will need to be a suitable level and form of traffic assessment to accompany the plan. (The transport case may consider the South East Wales Traffic Model as part of any masterplan impacts on the Strategic Road Network (SRN) (Wales Regional Transport Models | TfW)). The Council will also need to demonstrate that all housing components are deliverable through a housing trajectory prepared by the Council and Housing Stakeholder Group. Statements of Common Ground for key allocations, especially those that have ‘rolled over’ from the adopted plan, would be advantageous to demonstrate the sites are deliverable in the timescales set out.

Atodiadau:

Sylw

2 Dogfennau Ategol

ID sylw: 6087

Derbyniwyd: 11/03/2026

Respondent ID: 2669

Ymatebydd: Barratt Redrow Homes

Asiant : Lichfields

Effeithiau ar y Gymraeg:

N/A

Crynodeb o'r Gynrychiolaeth:

The RLDP housing trajectory shows a significant increase in delivery from about 200 dwellings per annum in 2025-26 and 2026-27 to approximately 1,000 dpa from 2027/28 to 2030/31. To achieve this, more available sites should be allocated in sustainable settlements, specifically land at Primrose Hill in Cowbridge, which can provide up to 220 dwellings at 50 per year. Including Primrose Hill in the RLDP would help ensure the plan’s delivery and meet the third soundness test.

Sylw

2 Dogfennau Ategol

ID sylw: 6588

Derbyniwyd: 06/03/2026

Respondent ID: 1029

Ymatebydd: Councillor Stephen Haines

Crynodeb o'r Gynrychiolaeth:

Monitoring Framework Enhancement
Include specific indicators for:
- Sustainable transport modal share.
- Retail provision delivery.
- Open space replacement.
- Infrastructure phasing compliance.

Atodiadau:

Cefnogi

2 Dogfennau Ategol

ID sylw: 6709

Derbyniwyd: 11/03/2026

Respondent ID: 1068

Ymatebydd: Persimmon Homes (East Wales)

Asiant : Asbri Planning

Crynodeb o'r Gynrychiolaeth:

Deposit Plan Appendix 1 - Housing Trajectory KS1
The identified delivery timescales and quantum of units for the site as set out at Appendix 1 of the Deposit Plan (as copied below) are agreed with and considered to be suitable/deliverable.

Persimmon Homes are committed to the delivery of the allocation, in accordance with the phasing trajectory outlined in the Deposit Plan. Further to the detailed submissions previously made, including extensive viability evidence which has been discussed in detail with the Local Authority and their viability consultant, it is confirmed that the site is viable and deliverable in accordance with the identified delivery timescales. It should be noted that there is a possibility that the number of units to be delivered within the first year (2028-2029) could be increased slightly, however, it is considered that the above presents a realistic trajectory for the site.

Atodiadau:

Gwrthwynebu

2 Dogfennau Ategol

ID sylw: 6710

Derbyniwyd: 11/03/2026

Respondent ID: 1068

Ymatebydd: Persimmon Homes (East Wales)

Asiant : Asbri Planning

Crynodeb o'r Gynrychiolaeth:

Deposit Plan Appendix 2 – Infrastructure Delivery Plan

A number of amendments to the text are requested in regard to the infrastructure requirements for KS1
North West Barry as set out within the Infrastructure Delivery Plan at Appendix 2 of the Deposit LDP.

Within the ‘Key site issues and constraints’ section of the Infrastructure Requirements table, the following amendments to the text are considered necessary:

• Proportionate access and junction arrangements on to the A4226 and a financial contribution
towards strategic highway network enhancements (in the context of the impact of wider committed developments on the strategic highway network).

As set out above, it is important that the required financial contribution towards strategic highway network enhancements is proportionate to the scale of the North West Barry development, and that additional committed developments, which would have a greater impact on the strategic highway network, are considered in the round.

• Previous desk-based assessment and site visits identified that development would have a major impact on five features (?), including important hedgerows which form historic boundaries. Archaeological features were also identified.

The above bullet point requires clarification as to the ‘five features’ which the development would have a ‘major impact’ upon. It should be noted that masterplanning work to date has been informed by extensive survey and assessment work which ensures that the proposed development is capable of addressing all constraints.
Within the section of the table where ‘broad costs’ of key infrastructure requirements are outlined, it is considered that the following amendments to the text are necessary:

• Education – Estimated Cost (£TBC) - DELETE COST CITED

It is considered that an estimated cost for education contributions cannot be specified at this stage, as the contribution will be directly related to current school capacity figures at the time of the Planning Application, with school capacities being fluid and subject to change. As such, the ‘circa’ figure should be removed from the text and replaced with ‘TBC’ at this point.

• A proportionate contribution towards on-site improvements to the capacity and flow of Weycock
Cross roundabout and other junctions on the strategic highways network where necessary (in the context of the impact of wider committed developments on the strategic highway network).

• VOGC to deliver improvements to junctions on the Strategic Highways Network using s106 contributions (from the North West Barry Key Site and other relevant commitments) .

As set out above, it is important that the required financial contribution towards strategic highway network enhancements is proportionate to the scale of the North West Barry development.

• Contribution towards off-site sustainable transport measures in the area as necessary and related
to the Key Site.

The requirement for a contribution towards off-site measures ‘in the area’ is not specific enough to provide certainty for the developer, and it will be important to ensure that any off-site measures are necessary and directly related to the North West Barry development.


Community Facilities – (£TBC) DELETE COST CITED
It is considered that an estimated cost for community facility contributions cannot be specified at this
stage – no background calculations are provided to evidence that this estimate is robust. As such, the
‘circa’ figure should be removed from the text and replaced with ‘TBC’ at this point.

Atodiadau:

Sylw

2 Dogfennau Ategol

ID sylw: 7226

Derbyniwyd: 09/03/2026

Respondent ID: 3520

Ymatebydd: Ms Lynne Squires

Crynodeb o'r Gynrychiolaeth:

The Plan does not clearly explain how progress will be monitored or how changes will be made if things do not go as planned. For example, if housing delivery is slower than
expected or infrastructure is delayed, there is little information on how allocations or policies would be adjusted.